ABOUT River Drivers Solar PROJECT

East Millinocket, Maine

Convalt is developing this 20 MW community solar project which would sell the electricity to the residents and businesses in East Millinocket, Maine starting with 5 MW. This project will help develop a sustainable community within East Millinocket providing new jobs and reducing the cost of electricity for residents and businesses of the community.

Status:  Mid-Stage Development
Location: East Millinocket, Maine
Phase 1 Construction Start Date: May 2023
Phase 1 Commercial Operation Date: September 2024
Capacity: 5 MW
Phase 2 Construction Start Date: March 2024
Phase 2 Commercial Operation Date: September 2025
Capacity: 15 MW

Project
Timeline

Phase 1 Timeline

June
2022

Project Development

Permits & Approvals

March
2023

May
2023

Construction Start Date

Commercial Operation Date

September
2023

Phase 2 Timeline

June
2023

Project Development

Permits & Approvals

August
2023

March
2024

Construction Start Date

Commercial Operation Date

September
2024

Project
Overview

Power Off-taker:

Community Solar & Direct to Consumers

Location:

East Millinocket, Maine

Surface Area:

21.5+ Acres

Commercial Operation Date:

September 2023 (Phase 1)

Value:

$6 million

Legal Advisor:

Eaton Peabody

Lenders Legal Advisor:

TBD

Lead Debt Arranger:

TBD

Master EPC:

Lincoln Infrastructure LLC

Project Status:

Date

Memorandum of Understanding (MOU)

August 2022

Purchase & Sale Agreement:

Not Applicable

Land Lease Agreement (LLA)

August 2022

Power Purchase Agreement (PPA)

February 2023

Limited Notice To Proceed(LNTP)

TBD

Engineering, Procurement and Construction (EPC)

TBD

Environment and Social Impact Assessment Approval Letter

TBD

Contact Us

We will be happy to answer all your questions! Convalt Energy operates multiple entities with one core mission: Make Earth Cool Again.
First and Last Name
Company
Phone
Valid
E-mail
Area of Interest
Message
0 / 500