ABOUT River Drivers Solar PROJECT

East Millinocket, Maine

Convalt is developing this 12 MW community solar project which would sell the electricity to the residents and businesses in East Millinocket, Maine starting with 2 MW. This project will help develop a sustainable community within East Millinocket providing new jobs and reducing the cost of electricity for residents and businesses of the community.

Status:  Mid-Stage Development
Location: East Millinocket, Maine
Phase 1 Construction Start Date: June 2024
Phase 1 Commercial Operation Date: December 2025
Capacity: 2 MW
Phase 2 Construction Start Date: January 2026
Phase 2 Commercial Operation Date:  January 2027
Capacity: 10 MW
riverdrivers_img3

Project
Timeline

Phase 1 Timeline

June
2022

Project Development

Permits & Approvals

December
2023

June
2024

Phase 1
Construction Start Date

Phase 1
Commercial Operation Date

December
2025

January
2026

Phase 2
Construction Start Date

Phase 2
Commercial Operation Date

January
2027

Project
Overview

Power Off-taker:

Community Solar & Direct to Consumers

Location:

East Millinocket, Maine

Surface Area:

21.5+ Acres

Commercial Operation Date:

December 2025 (Phase 1)

Value:

$6 million

Legal Advisor:

Eaton Peabody

Lenders Legal Advisor:

TBD

Lead Debt Arranger:

TBD

Master EPC:

Lincoln Infrastructure LLC

Project Status:

Date

Memorandum of Understanding (MOU)

August 2022

Purchase & Sale Agreement:

Not Applicable

Land Lease Agreement (LLA)

August 2022

Power Purchase Agreement (PPA)

February 2023

Limited Notice To Proceed(LNTP)

TBD

Engineering, Procurement and Construction (EPC)

TBD

Environment and Social Impact Assessment Approval Letter

TBD

Contact us

We will be happy to answer all your questions! Convalt Energy operates multiple entities with one core mission: Make Earth Cool Again.
First Name
Last Name
Company
E-mail
Phone
Valid
Business Unit Interest
Team Interest
Country of Interest
Message
0 / 500