Golden Eagle advances in Gallup

Council approval marks a development milestone for Convalt’s planned solar manufacturing campus.

KRQE reported a 3–2 Gallup City Council vote advancing Convalt’s proposed Golden Eagle manufacturing campus.

Site and partnership

The report identifies a 622-acre site on Carbon Coal Road, approximately five miles west of US 491, supported by Convalt’s binding land agreement with Gallup Land Partners.

Manufacturing-led campus

Plans combine solar manufacturing, dedicated power generation and water treatment. Convalt and Mayor Marc DePauli said the facility would not host third-party data-center operations.

Investment and employment

The mayor anticipated investment exceeding $1 billion over 24 months. Coverage projected approximately 1,000 construction jobs and 900 permanent positions, with construction expected to start in January and continue through 2028.

Reclaimed process water

The mayor cited a 2002 agreement allowing Gallup Land Partners access to one million gallons of treated wastewater daily, intended for manufacturing and cooling.

Community priorities

Councilor Sarah Piano recognized potential jobs and tax revenue while seeking stronger conditions covering water reuse, infrastructure costs, internal data use and decommissioning. Investment, employment and schedules remain projections.

Related projects & milestones

Watch the video

Watch on YouTube · Starts at 0:34