Grid infrastructure for Mandalay solar

An engineering contractor profile records the transmission and substation scope for Convalt’s Myanmar solar development.

RJE Global’s Myanmar project profiles identify Convalt Energy as the client for a turnkey engineering, procurement and construction contract signed in August 2017. The work supported a planned 300 MW AC solar development across two sites.

Connecting two solar sites

The contracted scope covered transformers and 230 kV/132 kV substations for Nabuaing and Wundwin, alongside extensions and upgrades at the remote Thapyewa and Myingyan switchyards.

A defined transmission package

RJE also listed the design, construction and commissioning of approximately 30 miles of double-circuit transmission line. The profile records the agreed infrastructure package and a planned ten-month delivery period, establishing the grid-connection work needed for the proposed solar plants.