Convalt Energy
Power Generation

Mandalay Solar

Mandalay Region, Republic of the Union of Myanmar

Mandalay Solar — company project imagery
SOLD

Project overview

Convalt’s historical Mandalay development comprises the proposed Nabuaing and Wundwin sites, each rated at 150 MW AC. Its record includes a government development agreement, a signed power purchase agreement and a contracted grid-connection package. Convalt describes the project as fully permitted and currently lists it as sold.

Company project information reviewed 13 October 2026. Planned figures describe development scope. View project source

Historical Development Capacity
300 MW AC · historical development scope
PPA Counterparty
Electric Power Generation Enterprise (“EPGE”)
Location
Central Mandalay Region, Myanmar
Reported Site Area
1,000 + 850 Acres
Historical Project Estimate
$250 million
Project track record

History & milestones.

Company track record

The project story

Mandalay’s development record includes a government agreement, a long-term electricity-sale contract and a signed grid-infrastructure engineering contract. Convalt currently lists the project as sold.

  1. 01
  2. 02
    POWER PURCHASE AGREEMENT SIGNED

    A pioneering solar PPA in Myanmar

    A listed-company disclosure records a Power Purchase Agreement signed on 28 March 2016 between Convalt Energy Myanmar Company Limited and Myanmar’s Electric Power Generation Enterprise. It covered 300 MWp and a 30-year electricity-sale term from commercial operation. A later JCIDA record described Convalt’s negotiated overseas PPAs, including Myanmar, as bankable.

    Sources & context

    The 30-year electricity-sale term begins at commercial operation. The March 2016 PPA and March 2022 agency record describe the contractual framework and subsequent assessment of bankability.

    View company milestone
  3. 03
    ENGINEERING CONTRACT SIGNED

    Myanmar grid-connection EPC contract secured

    RJE Global records signing a turnkey electrical-infrastructure EPC contract with Convalt in August 2017. The scope included 230 kV and 132 kV substations, transformer works and approximately 30 miles of transmission line to connect the two planned solar sites.

    Sources & context

    The engineering profile describes 300 MW AC; the PPA disclosure states 300 MWp. Each figure relates to its respective contractual scope.

    View company milestone
Project purpose

Intended benefits

The two-site plan connected electricity generation with the transmission infrastructure needed to reach the grid. Myanmar’s project register identifies proposed connections at Thapyawa for Wundwin and Myingyan for Nabuaing, with additional dry-season supply among Nabuaing’s intended benefits.