Attapeu solar development begins
Convalt began developing the Attapeu solar project in 2016, with an original planned scope of 250 MW AC.
Sources & context
The original studies covered 250 MW AC; the later development proposal expanded to 1,200 MW.
Attapeu Province, Lao P.D.R.
Convalt began developing the Attapeu solar project in southern Laos in 2016. The original studies addressed 250 MW AC; later reporting describes a 1,200 MW proposal and an August 2022 Project Development Agreement. The project remains under development.
Company project information reviewed 13 October 2026. Planned figures describe development scope. View project source
Attapeu’s record follows site investigation, government submissions and environmental work through a later development agreement. Historical studies concerned 250 MW; later reporting describes a 1,200 MW proposal.
Convalt began developing the Attapeu solar project in 2016, with an original planned scope of 250 MW AC.
The original studies covered 250 MW AC; the later development proposal expanded to 1,200 MW.
Convalt signed MOUs with the Ministry of Planning and Investment and provincial authorities for proposed solar developments in Bolikhamxay and Attapeu. The announced program totaled 300 MW.
The MOUs covered development work for the proposed solar projects.
The Attapeu project register records the terms of reference and scoping report as completed with the Ministry of Natural Resources and Environment.
Convalt signed letters of intent with GE, Cathay United Bank and DigiCollect for equipment, prospective financing and feasibility work. The program covered Attapeu and Bolikhamxay; U.S. and Lao officials witnessed the signing.
The letters of intent outlined prospective equipment, financing and feasibility-study partnerships.
Convalt’s Attapeu register records feasibility certificates as approved on 26 December 2017.
The approval related to the project’s feasibility studies.
Attapeu’s records list inception and quarterly feasibility reports submitted to the Lao government in Lao and English.
Convalt reports that its third feasibility-study issue was submitted four months early in November 2018 and received interim approval.
This milestone formed part of the project’s feasibility-study process.
The Attapeu register records its environmental-compliance certificate milestone as complete on 13 December 2018.
This entry records the environmental-compliance milestone in December 2018.
The Laotian Times reports that Convalt signed an Attapeu Project Development Agreement in August 2022. Its October 2025 coverage describes a planned 1,200 MW solar development.
The August 2022 agreement was covered in October 2025 reporting, which described continuing concession and power-purchase preparations.
Concession and power-purchase preparations were continuing in October 2025.
Historical study milestones do not establish commercial operation. The October 2025 report identified concession and power-purchase preparations as continuing work.
Attapeu’s planned export market is Vietnam, linking solar development in southern Laos with regional electricity demand. The record includes site investigation, feasibility work and environmental-compliance documentation supporting that development process.